Multiple Choice Questions (MCQ) On Estimating and Costing (PART 2)

 

11. In this method approximate total length of walls is found in running meter and this total length multiplied by the rate per running meter of wall gives a fairly accurate cost.

a) Annual Reair Estimate

b) Item Rate Estimate

c) Approximate Quantity Method Estimate

d) Cubical Content Estimate

Answer: c) Approximate Quantity Method Estimate

 

12. The approximate cost of a building of cubic content of 400 cum @ Rs. 180/- per cum is..........

a) Rs. 92000/-

b) Rs. 12000/-

c) Rs. 72000/-

d) Rs. 42000/-

Answer: c) Rs. 72000/-

 

13. To prepare approximate estimate of a godown building, method of approximate estimatesuitable is..................

a) Plinth Area Method

b) Service Unit Method

c) Cubical Content Method

d) Typical Bay Method

Answer: d) Typical Bay Method

 

14. While preparing approximate estimate of water supply projects the unit to be adopted to arrive at approximate cost is.......

a) Area Served by the Project

b) Population Served by the Project

c) All the above

Answer: c) All the above

 

15. For canals, approximate estimate is prepared on the basis of........

a) Per Km

b) Per cubic meter capacity of canal

c) Per hectare of command area

d) All the above

Answer: d) All the above

 

16. For steel bridge suitable method of approximate estimate is ........

a) Plinth Area Method

b) Cubical Content Method

c) Typical Bay Method

d) Service Unit Method

Answer: c) Typical Bay Method

 

17. The most reliable estimate is ........

a) Detailed estimate

b) Preliminary estimate

c) Plinth Area estimate

d) Cube Rate estimate

Answer: a) Detailed estimate

 

18. The brickwork is measured in sq meter, in case of..........

a) Honey combed brickwork

b) Brick flat soling

c) Half brick walls or the partition

d) All the above

Answer: d) All the above

 

19. Brick walls are measured in sq meter, if the thickness of wall is..........

a) 10 cm

b) 15 cm

c) 20 cm

d) None of the above

Answer: a) 10 cm

 

20. As per IS 1200, area is measured nearest to..........

a) 0.01 sqm

b) 0.02 sqm

c) 0.03 sqm

d) 0.05 sqm

Answer: a) 0.01 sqm

 