Multiple Choice Questions (MCQ) On Estimating and Costing (PART 2)

 

11. In this method approximate total length of walls is found in running meter and this total length multiplied by the rate per running meter of wall gives a fairly accurate cost.

a) Annual Reair Estimate

b) Item Rate Estimate

c) Approximate Quantity Method Estimate

d) Cubical Content Estimate

Answer: c) Approximate Quantity Method Estimate

 

12. The approximate cost of a building of cubic content of 400 cum @ Rs. 180/- per cum is..........

a) Rs. 92000/-

b) Rs. 12000/-

c) Rs. 72000/-

d) Rs. 42000/-

Answer: c) Rs. 72000/-

 

13. To prepare approximate estimate of a godown building, method of approximate estimatesuitable is..................

a) Plinth Area Method

b) Service Unit Method

c) Cubical Content Method

d) Typical Bay Method

Answer: d) Typical Bay Method

 

14. While preparing approximate estimate of water supply projects the unit to be adopted to arrive at approximate cost is.......

a) Area Served by the Project

b) Population Served by the Project

c) All the above

Answer: c) All the above

 

15. For canals, approximate estimate is prepared on the basis of........

a) Per Km

b) Per cubic meter capacity of canal

c) Per hectare of command area

d) All the above

Answer: d) All the above

 

16. For steel bridge suitable method of approximate estimate is ........

a) Plinth Area Method

b) Cubical Content Method

c) Typical Bay Method

d) Service Unit Method

Answer: c) Typical Bay Method

 

17. The most reliable estimate is ........

a) Detailed estimate

b) Preliminary estimate

c) Plinth Area estimate

d) Cube Rate estimate

Answer: a) Detailed estimate

 

18. The brickwork is measured in sq meter, in case of..........

a) Honey combed brickwork

b) Brick flat soling

c) Half brick walls or the partition

d) All the above

Answer: d) All the above

 

19. Brick walls are measured in sq meter, if the thickness of wall is..........

a) 10 cm

b) 15 cm

c) 20 cm

d) None of the above

Answer: a) 10 cm

 

20. As per IS 1200, area is measured nearest to..........

a) 0.01 sqm

b) 0.02 sqm

c) 0.03 sqm

d) 0.05 sqm

Answer: a) 0.01 sqm

 

Comments

  1. Very gud information. I'm inspired by you and I have create a same blog like as your https://draughtsmancivilengineering.blogspot.com

    ReplyDelete

Post a Comment

Popular posts from this blog

How to Use Optical Square and Open Cross Staff

Offsets can be accurately set up, particularly long offsets, by use of optical instruments like cross staff or optical square etc.    a) Cross Staff:             Two pairs of vertical slits, mounted orthogonally on a pole staff constitutes a simple instrument for setting out normal offsets as depicted in Figure. Each pair of slits can form a line of sight. It is fixed on a stand. Two persons are required to operate cross staff. Use of cross staff: 1. To find a foot of perpendicular on chain line 2. To set out the perpendicular from a given point.   b) Optical Square: It may be noted that at least two surveyor’s are required to set normal offsets while using cross staff. This disadvantage can be overcome if optical square is used for this purpose as only single surveyor can perform this task. Principle of optical square:   The angle between the first incident ray and the final reflected ray is twice that of t...

Direct and Indirect Ranging

  Measurement of distances with Chain and Tape on ground with Direct and Indirect Ranging   Principle of Chain Surveying:            The principle of chain surveying is derived from principle of triangulation. The area to be surveyed is divided into a number of triangles and the sides of the triangle are measured in the field. To get good results in plotting, the framework should consist of triangles which are as nearly equilateral as possible. Preferably all the sides of a triangle should be nearly equal having each angle nearly 60 o  to ensure minimum distortion due to errors in measurements of sides and plotting.   Theory:        The process of establishing intermediate point on a straight line between two end points is known as  ranging . Ranging must be done before a survey line is chained. It may be necessary to establish a number of intermediate points prior to chaining w...

Rolled Steel Sections

  Rolled Steel Sections       Structural steel sections are hot rolled into different shapes and sizes to form the different sections. Cross section and size are governed by functional requirements, dimensional and weight capacity of rolling mills, arrangement of material for optimum structural efficiency. In a rolling mill molten steel from furnace is poured into continuous casting system where steel solidifies but it is not allowed to cool completely. Then hot steel passes through series of rollers. Such series of rollers squeezes steel into desired cross sectional shape. If the load to be resisted is small single rolled steel sections are used. If the single section is insufficient, single sections are combined or built up with angles/ channels/ I sections with or without cover plates and /or laced, providing sufficient resistance to heavy loads. Most commonly used hot rolled steel shapes are as follows: 1. Rolled Steel I -Sections 2. Rolled Steel C...