71. In absence of detailed design the percentage of steel in
concrete slab is usually taken as..........
a) 0.5 to 0.8 % of quantity of concrete in cu.m
b) 0.7 to 1.0 % of quantity of concrete in cu.m
c) 1.0 to 2.0 % of quantity of concrete in cu.m
d) 1.0 to 5.0 % of quantity of concrete in cu.m
Answer: b) 0.7 to 1.0 % of quantity of concrete in cu.m
72. When small items are
estimated for which detailed quantities can not be taken out, they are
considered as..........
a) Lump sum
b) Contingencies
c) Sundries
d) None of these
Answer: a) Lump sum
73. The expected out turn
of RCC work per mason per day is .........
a) 1 cu.m
b) 1.25 cu.m
c) 3 cu.m
d) 5 cu.m
Answer: c) 3 cu.m
74. The volume of dry
material required for 1 cum of wet concrete is .....
a) 1.52 to 1.54 cu.m
b) 1.59 to 1.62 cu.m
c) 1.57 to 1.59 cu.m
d) 1.55 to 1.57 cu.m
Answer: a) 1.52 to 1.54 cu.m
75. Select the incorrect
statement from the following
a) Rate analysis helps to control the consumption of material on
site
b) Rate analysis plays importsant role in allocation of
labours on site
c) Rates calculated by rate analysis are exact are will be
same for different places
d) Rate analysis is a judgemental process
Answer: c) Rates calculated by rate analysis are exact
are will be same for different places
76. Number of cement bags
required for 2500 kg of cement are..........
a) 50
b) 100
c) 200
d) 500
Answer: a) 50
77. Which of the following
is not the category of labour?
a) Skilled labour
b) Unskilled labour
c) Semi-skilled labour
d) Semi-unskilled labour
Answer: d) Semi-unskilled labour
78. Select the correct
option from the following
a) As per rate analysis, for the work which is going to continue
for more period; for that work rates are less.
b) If the site is situated in hilly areas or in extreme weather
condition then rates are more as per rate analysis
c) Both a) and b) are correct
d) Both a) and b) are incorrect
Answer: c) Both a) and b) are correct
79. In mid section formula,
pick up correct statement
a) The mean depth is average of the depths of two consecutive
sections
b) The area of mid sections is calculated by using mean depth
c) The volume of earthwork is calculated by multiplying the
mid section area by the distance between two sections
d) All the above
Answer: d) All the above
80. The assumption on which
the trapezoidal formula for volume is based is ..........
a) The end sections are parallel planes
b) The mid area of a pyramid is half the average area of the
ends
c) The volume of the prismoidal is over estimated and hence a
prismoidal correction is applied
d) All the above
Answer: d) All the above
Comments
Post a Comment