51. The method suitable for calculating quantities of rectangular,
circular and polygonal buildings is.......
a) Long wall and Short wall method
b) PWD method
c) Centre Line method
d) All the above
Answer: c) Centre Line method
52. The procedure of
calculating cost of item of work is known as..........
a) Taking out quantities
b) Squaring
c) Abstracting
Answer: c) Abstracting
53. Factor affecting task
work is..........
a) Climatic condition
b) Technique adopted
c) Location of work
d) All the above
Answer: d) All the above
54. Contractor's profit
considered during rate analysis of item of work is..........
a) 5 %
b) 10 %
c) 15 %
d) 20 %
Answer: b) 10 %
55. Number of traditional
(19 X 9 X 9 cm) brick required per 1 cu.mBBM construction is...........
a) 50 nos.
b) 500 nos.
c) 5000 nos.
d) 5500 nos.
Answer: b) 500 nos.
56. ........... include
general office expenses, rents, taxes, supervision and other costs which are
indirect expenses and not productive expenses on the job.
a) Total costs
b) General costs
c) Overhead costs
d) Contingencies
Answer: c) Overhead costs
57. The capacity of doing
work by an artesian or skilled labour in the form of quantity of work per dayis
known as..........
a) Over-turn
b) In-turn
c) Out-turn
d) Out-come
Answer: c) Out-turn
58. Normal or standard lead
is equal to ..........
a) 10 m
b) 20 m
c) 30 m
d) 40 m
Answer: c) 30 m
59. Standard lift is taken
as equal to ..........
a) 1.0 m
b) 1.5 m
c) 2.0 m
d) 2.5 m
Answer: b) 1.5 m
60. The correct prismoidal
formula for volume is...........
a) L X [ First Area + Last Area + ∑Even Area + 2 ∑Odd Areas]
b) L/3 X [ First Area + Last Area + 4 ∑Even Area +
2 ∑Odd Areas]
c) L/3 X [ First Area + Last Area + 2 ∑Even Area +
4 ∑Odd Areas]
d) L/6 X [ First Area + Last Area + 2 ∑Even Area +
4 ∑Odd Areas]
Answer: b) L/3 X [ First Area + Last Area + 4 ∑Even Area
+ 2 ∑Odd Areas]