41. To make out an estimate for a work, the data required is
Drawing, Specification and........
a) Materials
b) Labours
c) Rates
d) Transportation
Answer: c) Rates
42. A large work or project
may consist of several building or small works and each of these work is known
as.........
a) Sub-work
b) Sub-project
c) Sub-head
d) Sub-construction
Answer: a) Sub-work
43. The term ......... is
used to denote a procedure of costing or valuing an item of work on the basis
of actual labours and materials required.
a) Prime cost
b) Hour work
c) Day work
d) Sub-work
Answer: c) Day work
44. If L is length of item
then according to centre line method, L is........
a) L = Total c/c length - 1/2 number of junctions X Width of item
b) L = Total c/c length + 1/2 number of junctions X Width of
item
c) L = Total c/c length - 1/4 number of junctions X Width of
item
d) L = Total c/c length - 1/4 number of junctions X Width of
item
Answer: a) L = Total c/c length - 1/2 number of junctions X
Width of item
45. Long wall and short
wall method is adopted for structures where there are........
a) More offset
b) No offset
Answer: b) No offset
46. Quick method of
calculating quantities of different items is..........
a) Long wall and Short wall method
b) Centre Line method
Answer: b) Centre Line method
47. Length of long wall
........from foundation towards superstructure
a) Increasing
b) Decreasing
c) Remains same
Answer: b) Decreasing
48. Length of short wall
........from foundation towards superstructure
a) Increasing
b) Decreasing
c) Remains same
Answer: a) Increasing
49. Weight per meter length
of 12 mmdiameter steel bar is.....
a) 0.89
b) 0.62
c) 0.39
d) 0.22
Answer: a) 0.89
50. Work supervisors,
chaukidars, other temporary workers who are employed during execution of work,
the payment of above workers are done from.........................
a) Day work
b) Contingencies
c) Work charged establishment
d) All the above
Answer: c) Work charged establishment