Skip to main content

Multiple Choice Questions (MCQ) On Estimating and Costing (PART 1)

 

1. The process of calculating the quantities and costs of the various items required in connection with the work for its satisfactory completion is called as.......

a) Costing

b) Estimating

c) Estimate

d) Detailed Estimate

Answer: b) Estimating

 

2. The process of determining the actual cost of the work before the execution of work is called as .......

a) Costing

b) Estimating

c) Estimate

d) Detailed Estimate

Answer: a) Costing

 

3. When the original sanctioned estimate is likely to exceed by more than 5%, estimate prepared is..........

a) Revised and Supplementary Estimate

b) Revised  Estimate

c) Supplementary Estimate

d) All the Above

Answer: b) Revised Estimate

 

4. When the expenditure on a work exceeds or likely to exceeds the amount of administrative sanctioned by more than 10%, estimate prepared is...........

a) Revised and Supplementary Estimate

b) Revised  Estimate

c) Supplementary Estimate

d) All the Above

Answer: b) Revised Estimate

 

5. If there is change of rate or quantity of materials, estimate prepared is...........

a) Revised and Supplementary Estimate

b) Revised  Estimate

c) Supplementary Estimate

d) All the Above

Answer: b) Revised Estimate

 

6. When additional works or changes are required to supplement the original works, during the execution of work then estimate prepared is called as...........

a) Revised and Supplementary Estimate

b) Revised  Estimate

c) Supplementary Estimate

d) All the Above

Answer: c) Supplementary Estimate

 

7. Plinth area rate method is ................ type of method.

a) Detailed Estimate

b) Approximate  Estimate

c) Revised Estimate

d) British Detailed Method

Answer: b) Approximate  Estimate

 

8. .................. estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.

a) Revised and Supplementry Estimate

b) Maintenance  Estimate

c) Item Rate Estimate

d) Revised Estimate

Answer: b) Maintenance  Estimate

 

9. Approximate cost of a hostel building for 100 students @ Rs. 1000/- per student works out as Rs. 10 lakhs.

a) True

b) False

Answer: a) True

 

10. .................. is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and constriction, in the locality.

a) Cube Rate Estimate

b) Supplementry  Estimate

c) Maintenance Estimate

d) Plinth Area Estimate

Answer: d) Plinth Area Estimate

Comments

Popular posts from this blog

Rolled Steel Sections

  Rolled Steel Sections       Structural steel sections are hot rolled into different shapes and sizes to form the different sections. Cross section and size are governed by functional requirements, dimensional and weight capacity of rolling mills, arrangement of material for optimum structural efficiency. In a rolling mill molten steel from furnace is poured into continuous casting system where steel solidifies but it is not allowed to cool completely. Then hot steel passes through series of rollers. Such series of rollers squeezes steel into desired cross sectional shape. If the load to be resisted is small single rolled steel sections are used. If the single section is insufficient, single sections are combined or built up with angles/ channels/ I sections with or without cover plates and /or laced, providing sufficient resistance to heavy loads. Most commonly used hot rolled steel shapes are as follows: 1. Rolled Steel I -Sections 2. Rolled Steel C...

How to Use Optical Square and Open Cross Staff

Offsets can be accurately set up, particularly long offsets, by use of optical instruments like cross staff or optical square etc.    a) Cross Staff:             Two pairs of vertical slits, mounted orthogonally on a pole staff constitutes a simple instrument for setting out normal offsets as depicted in Figure. Each pair of slits can form a line of sight. It is fixed on a stand. Two persons are required to operate cross staff. Use of cross staff: 1. To find a foot of perpendicular on chain line 2. To set out the perpendicular from a given point.   b) Optical Square: It may be noted that at least two surveyor’s are required to set normal offsets while using cross staff. This disadvantage can be overcome if optical square is used for this purpose as only single surveyor can perform this task. Principle of optical square:   The angle between the first incident ray and the final reflected ray is twice that of t...

Usefulness of Slump Test

Slump test can be employed either in laboratory or at site of work for measuring consistency of concrete. This test is used conveniently as a control test and gives an indication of the uniformity of concrete from batch to batch. Repeated batches of the same mix, brought to the same slump, will have the same water content and water cement ratio, provided the weights of aggregate, cement and admixtures are uniform and aggregate grading is within acceptable limits. Additional  information on workability and quality of concrete can be obtained by observing the manner in which concrete slumps. Figure: Typical Mould for Slump Test If concrete slumps evenly it is called  true slump . If one half of the cone slides down, it is called  shear slump . In case of shear slump, the slump value is measured as the difference in height between the height of the mould and the average value of the subsidence. Shear slump also indicates that the concrete is non cohesive and shows the charac...