 21. According to the IS code 456:2000, the maximum spacing between the vertical stirrups should not be greater than  ..........

a) 0.7 d or 200 mm whichever is less

b) 0.75 d or 200 mm whichever is less

c) 0.7 d or 300 mm whichever is less

d) 0.75 d or 300 mm whichever is less

Answer: d) 0.75 d or 300 mm whichever is less

 

 22. Following is the forms of shear reinforcement used in beam  ..........

a) Vertical stirrups

b) Inclined stirrups

c) Bent up bars

d) All the above

Answer: d) All the above

 

 23. For M 20 grade concrete value of design bond stress for plain bars in tension is ..........

a) 1.6

b) 1.2

c) 1.3

d) 1.5

Answer: b) 1.2

 

 24. According to IS code, Maximum shear stress resisted by M 20 concrete is  ..........

a) 2.5 N/mm2

b) 2.8 N/mm2

c) 3.1 N/mm2

d) 3.5 N/mm2

Answer: b) 2.8 N/mm2 

 

 25. The shear reinforcement in the R.C.C. is provided to resist..........

a) Vertical shear

b) Horizontal shear

c) Diagonal compression

d) Diagonal tension

Answer: d) Diagonal tension

 

 26. The shear reinforcement in R.C.C. is provided when ..........

a) The design shear strength of concrete exceeds nominal shear stress

b) Nominal shear stress exceeds the design shear strength of concrete

c) Nominal shear stress equal to the design shear strength of concrete

d) All the above

Answer:  b) Nominal shear stress exceeds the design shear strength of concrete

 

 27. Anchorage value of 45 degree bend for 16 mm diameter bar is.........

a) 16 mm

b) 32 mm

c) 64 mm

d) 80 mm

Answer:  c) 80 mm

 

 28. According to IS 456:2000, overlapping length of bars in flexural tension should be..... 

a) Greater of two times of development length or thirty times of diameter of bar

b) Greater of development length or thirty times of diameter of bar

c) Greater of two times of development length or twenty four times of diameter of bar

d) Greater of development length or twenty four times of diameter of bar

Answer:  b) Greater of development length or thirty times of diameter of bar

 

 29. If aspect ratio is 1.2 then type of slab is..........

a) One way slab

b) Two way slab

Answer:  b) Two way slab

 

 30. If mild steel is to be used for slab reinforcement, then minimum area of reinforcement will be ..........

a) 0.12 % of gross area of slab

b) 0.15 % of gross area of slab

c) 0.18% of gross area of slab

d) 0.20% of gross area of slab

Answer:  b) 0.15 % of gross area of slab


Comments

Popular posts from this blog

How to Use Optical Square and Open Cross Staff

Offsets can be accurately set up, particularly long offsets, by use of optical instruments like cross staff or optical square etc.    a) Cross Staff:             Two pairs of vertical slits, mounted orthogonally on a pole staff constitutes a simple instrument for setting out normal offsets as depicted in Figure. Each pair of slits can form a line of sight. It is fixed on a stand. Two persons are required to operate cross staff. Use of cross staff: 1. To find a foot of perpendicular on chain line 2. To set out the perpendicular from a given point.   b) Optical Square: It may be noted that at least two surveyor’s are required to set normal offsets while using cross staff. This disadvantage can be overcome if optical square is used for this purpose as only single surveyor can perform this task. Principle of optical square:   The angle between the first incident ray and the final reflected ray is twice that of t...

Direct and Indirect Ranging

  Measurement of distances with Chain and Tape on ground with Direct and Indirect Ranging   Principle of Chain Surveying:            The principle of chain surveying is derived from principle of triangulation. The area to be surveyed is divided into a number of triangles and the sides of the triangle are measured in the field. To get good results in plotting, the framework should consist of triangles which are as nearly equilateral as possible. Preferably all the sides of a triangle should be nearly equal having each angle nearly 60 o  to ensure minimum distortion due to errors in measurements of sides and plotting.   Theory:        The process of establishing intermediate point on a straight line between two end points is known as  ranging . Ranging must be done before a survey line is chained. It may be necessary to establish a number of intermediate points prior to chaining w...

Rolled Steel Sections

  Rolled Steel Sections       Structural steel sections are hot rolled into different shapes and sizes to form the different sections. Cross section and size are governed by functional requirements, dimensional and weight capacity of rolling mills, arrangement of material for optimum structural efficiency. In a rolling mill molten steel from furnace is poured into continuous casting system where steel solidifies but it is not allowed to cool completely. Then hot steel passes through series of rollers. Such series of rollers squeezes steel into desired cross sectional shape. If the load to be resisted is small single rolled steel sections are used. If the single section is insufficient, single sections are combined or built up with angles/ channels/ I sections with or without cover plates and /or laced, providing sufficient resistance to heavy loads. Most commonly used hot rolled steel shapes are as follows: 1. Rolled Steel I -Sections 2. Rolled Steel C...